In the last few months, we dove deep into the latest IEEE 1584 – 2018 updates. We looked at the impact it has had on Arc Flash Compliance and how we can better build an effective Arc Flash Risk Assessment from it. In this blog, we are going to look at real case studies comparing Arc Flash Risk Assessments that were done Prior to the IEEE 1584 – 2018 update and studies that were recently updated with the new standard. The results are so significant that we can clearly see that lives can be saved, injuries can be prevented, and property damage can be avoided.

For a quick review, the 2018 release brought with it 16 years’ worth of changes.

  • More than 6x the number of tests were performed to derive the 2018 1584 calculation model vs. the 2002 model.
  • The 2018 model test setups consisted of using different size metal enclosures and bus orientations.
  • There are no longer exceptions that allow for “generic” labels (<125kVA rule)

Because of this IEEE 1584-2018, Annex G section G.1 states – “It is the conclusion that this model produces results that are more accurate than those of its predecessor for configurations common in both models. Further, the new model provides a method to evaluate the incident energy for other configurations not previously considered, such as vertical conductors in a box with a barrier and horizontal conductors in a box and without a box.”  

Arc Flash Results Comparison

The Incident Energy levels vary substantially when comparing the 2002 and 2018 IEEE-1584 standards of calculation. We are going to take a look at 4 different facilities so we can have a good variety of examples. The first Table is a Manufacturing Plant that has 98 pieces of equipment modeled.

Facility Type Manufacturing
# Of Equipment 98
PPE Range 1584-2002 1584-2018
Cat 0 (<1.2 cal/cm²) 44 46
Cat 2 (1.2-12 cal/cm²) 43 45
Cat 4 (12-40 cal/cm²) 5 4
DANGER (>40cal/cm²) 6 3

The Facility has buses that fall into very similar PPE ranges across the board except for that 3 of the previously non-workable locations are now <40 cal. These 3 pieces most likely were Incoming switchgear or switchboards that would not be safe to work on energized and now are. That means no shutdowns are needed to perform Infrared, change fuses, or not having to perform expensive remote disconnecting to verify power is shut off.

The next table is a Data Center with 273 pieces of equipment that have great varying differences in calculated IE values between the 2 standards.

Facility Type Datacenter/Office
# Of Equipment 273
PPE Range 1584-2002 1584-2018
Cat 0 (<1.2 cal/cm²) 147 81
Cat 2 (1.2-12 cal/cm²) 80 141
Cat 4 (12-40 cal/cm²) 29 36
DANGER (>40cal/cm²) 17 15

Cat 0 and Cat 2 quantities essentially swapped and there are many more locations that require 12 cal PPE. That means for the 5 years in between studies, workers were potentially exposed to higher Incident energy (if working energized) and were probably not wearing the proper PPE that would protect them. Also, we again see 2 less non-workable locations in locations can now be workable with a 40-cal suit.

Now let us look at a College Campus that has 176 pieces of equipment analyzed.

Facility Type College Campus
# Of Equipment 176
PPE Range 1584-2002 1584-2018
Cat 0 (<1.2 cal/cm²) 103 106
Cat 2 (1.2-12 cal/cm²) 46 51
Cat 4 (12-40 cal/cm²) 12 11
DANGER (>40cal/cm²) 15 8

Once again, not many differences in PPE categories, however, there are 7 more workable locations with the new standard applied.

In our last example, we are going to look at a 30 story High Rise Office building with 177 pieces of equipment modeled.

 

Facility Type Office
# Of Equipment 177
PPE Range 1584-2002 1584-2018
Cat 0 (<1.2 cal/cm²) 101 106
Cat 2 (1.2-12 cal/cm²) 59 66
Cat 4 (12-40 cal/cm²) 12 2
DANGER (>40cal/cm²) 5 3

 

There are a few less Cat 0’s and a few more Cat 2’s, but there are 10 Cat 4 locations that went away and again 2 more workable locations that were DANGER before.

In the end, we are seeing a lot of non-workable locations going away but more importantly, we are seeing a significant change in locations that were previously less dangerous than before. Again, we have proof the accuracy from the 1584-2018 update is helping us ensure that we are protecting workers and property from dangerous electrical conditions.

The 125kVA exception rule is gone…finally!

  • The 125kVA exception in the 1584-2002 stated that electrical equipment fed from transformers <125kVA at <240V did not pose any significant arc flash hazard. After years of much debate and more testing revealed that this is not the case.
    • Because of this, more equipment must be included in the analysis one-line model in order for a label to be generated. Previously, labels with a value of ”<1.2cal/cm2” could have been installed by inspection.
    • This rule is no longer there, thus more equipment must be included in the actual model.
    • Depending on the facility, this can be upwards of 50% or higher.

The following illustrations are from the same College Campus we took a look at earlier. The red equipment shows all equipment fed from transformer < 125kVA. As we see, this equipment would not be included with the old exception rule.

RED

 

The next illustration shows worst-case Incident Energy categories for this equipment.

orange lines image

Adding these to the model and running the calculations based on the new standard shows that there are many locations (over half) that are >1.2cal/cm2. This means that in the event of an arc flash, the worker would NOT have the appropriate PPE.

MISCONCEPTION: In an arc flash, equipment directly downstream of a transformer trips the protective device directly upstream of it (if coordinated properly, maintained, etc.). The transformer makes the current pass more slowly and thus the clearing time is longer and results in HIGHER incident energy on the secondary. Often people think that working at 208V does not pose as great of a risk for arc-flash but often times this is quite the contrary.

In closing, the significance of applying the new standard delivers 3 major advantages.

Safety:

  • More accurate results will lead to more accurate PPE requirements. If site personnel are not wearing appropriate PPE, arc-flash can lead to significant injury or death.
  • We have seen many locations that were previously deemed <1.2cal/cm that now require level 2 or 4 PPE. Particularly the case with equipment with smaller enclosure sizes and equipment that used to be <1.2cal by default based on old 1584 language (i.e., <125kVA cutoff)

Maintenance:

  • In our studies so far, we have seen many locations that were previously non-workable become workable. Particularly the case at switchboards
  • We have also seen locations that required arc-flash suits per the old standard now no longer need them. Particularly the case at equipment with larger enclosure sizes

Compliance:

  • This standard is not voluntary, it is more of a declaration of how to meet the existing standards already in place. In order to meet engineering best practices, this standard NEEDS to be followed. OSHA points to 70E which points to 1584, end of the story. You can’t have a safe work environment per OSHA requirements and be using inappropriate electrical PPE.

If you need any help developing an effective Arc Flash study, please contact us. We have extensive knowledge of electrical safety as this is our only focus. Many other engineering firms perform arc-flash risk assessment studies as filler work and do not possess detailed knowledge of the standards and how to apply them correctly.